Date
1 - 2 of 2
B @ D 0.9 Gold Master
Robert Marshall <robert.marshall@...>
We are about to close https://gitlab.com/cip-project/testing/issues/85 -
B @ D 0.9 Gold Master declaration and thus we are declaring that the Gold Master for release 0.9 is ready and we will move onto the deployment phase (issue 86). Thank you for your support, encouragement and even (especially?) the bug reports. Robert
|
|
Agustin Benito Bethencourt <agustin.benito@...>
Hi,
On 16/05/17 15:01, Robert Marshall wrote: We are about to close https://gitlab.com/cip-project/testing/issues/85 -So the release of B@D is scheduled for May 23rd at 11:00 UTC Now we will concentrate in the following tasks: * Deployment: #86 https://gitlab.com/cip-project/testing/issues/86 * Other release related tasks you can follow from #37 https://gitlab.com/cip-project/testing/issues/37 Best Regards -- Agustin Benito Bethencourt Principal Consultant - FOSS at Codethink agustin.benito@...
|
|